Duration.Days
The whole days of a duration, leaving out the hours, minutes and seconds beyond them.
Group: Dates and times. Power Query M has it too: a query that uses it is written as in Power BI.
Syntax
Duration.Days(duration as nullable duration) as nullable number
| Parameter | Type | Description |
|---|---|---|
duration | nullable duration | The duration; null gives null. |
Returns
nullable number. The number of whole days.
Remarks
- This is a part, not a total: 2 days and 19 hours give 2, where
Duration.TotalDaysgives about 2.79. - A negative duration gives negative parts.
Examples
Two days and a bit
Duration.Days(#duration(2, 5, 30, 0))
2
A delivery time
Duration.Days(#datetime(2024, 3, 18, 10, 0, 0) - #datetime(2024, 3, 15, 14, 30, 0))
2
From 15 March 14:30 to 18 March 10:00 is 2 days, 19 hours and 30 minutes.